2008 School Bond Election
Scope of Work for Critical Renovations
At several schools across the District, air quality systems, designed around out-dated and no longer appropriate technology,
are at the end of their useful lives. These geothermal ground-loop or earth-coupled heat pump systems need to be replaced with more reliable and sustainable systems.
In addition, AISD construction management staff developed a list of immediate needs at various campuses, such as needed restroom repairs.
If these items are left unattended, much more expensive remediation would be required in the long run. Additional projects needing immediate attention were submitted by principals
and various districtwide departments. These projects also include items presented during the public forums.
HEALTH & SAFETY
| Bailey MS | Convert darkroom to ADA-compliant student restroom |
| Baker Center | Install ADA-compliant elevator and create accessible exterior pathway |
| Barton Hills ES | Renovate/expand adult restrooms |
| Doss ES | Replace electric drinking fountains |
| Fulmore MS | Renovate student and faculty restrooms |
| Kealing MS | Construct direct exitway from cafeteria |
| Kealing MS | Construct direct exitway from science classrooms 109A & B |
| McCallum HS | Renovate student and faculty restrooms |
| Reagan HS | Install additional exterior security lighting at south parking lot |
| St. Elmo ES | Construct additional set of student and faculty restrooms |
| Sims ES | Extend/replace security fencing at main entry |
| Small MS | Install additional exterior security and stairway lighting |
| Small MS | Construct enclosure for three-story exterior stairway |
| Webb MS | Install ADA-compliant elevator |
| Zilker ES | Renovate group student restrooms for ADA compliance, install wheelchair lift at stage, and make modifications to accessible route to student pick up area |
TOTAL $5,586,002
INDOOR AIR QUALITY/HEATING, VENTILATION and AIR-CONDITIONING (HVAC) SYSTEMS
| Anderson HS | Replace selected HVAC system equipment |
| Andrews ES | Replace HVAC system equipment in administration area |
| Ann Richards School for Young Women Leaders | Replace selected HVAC system equipment in two-story classroom wing |
| Bailey MS | Replace HVAC system equipment at cafeteria, gymnasium and administration area |
| Baker Center | Replace selected HVAC system equipment |
| Becker ES | Replace HVAC system equipment at cafeteria and gymnasium, and install new digital controls |
| Boone ES | Replace HVAC system equipment at cafeteria, gymnasium, library, and selected classrooms |
| Bowie HS | Install digital HVAC controls to replace deteriorated pneumatic systems |
| Brentwood ES | Replace HVAC system equipment in the administration area |
| Brooke ES | Replace HVAC system equipment at cafeteria and 100-classroom wing, and install new digital controls |
| Brown ES | Replace HVAC system equipment at library |
| Burnet MS | Replace HVAC system cooling tower |
| Clifton Center | Replace selected HVAC system equipment |
| Covington MS | Replace HVAC system equipment at large gym, career education building, and computer lab |
| Dawson ES | Replace HVAC system equipment at cafeteria and library, and provide digital controls |
| Dobie MS | Replace HVAC system equipment at band hall and orchestra room |
| Doss ES | Replace HVAC system equipment at 300-classroom wing |
| Garza HS | Replace HVAC system cooling tower and heat exchanger |
| Govalle ES | Replace HVAC system equipment at kitchen, cafeteria, and 200 & 500-classroom wings |
| Johnston HS | Replace HVAC system at large gymnasium |
| Jordan ES | Replace HVAC system equipment at kitchen, and install new digital controls |
| Kiker ES | Install supplemental conditioned fresh air system at classroom wings |
| Lanier HS | Replace HVAC system equipment at agriculture building |
| LBJ HS | Replace HVAC system equipment at gymnasium |
| McCallum HS | Replace HVAC system equipment at math classroom wing |
| Mendez MS | Replace HVAC system equipment at cafeteria |
| Norman ES | Replace central HVAC system chilling plant |
| Oak Hill Anx ES | Replace selected HVAC system equipment at administration area |
| Oak Hill ES | Replace selected HVAC system equipment at cafeteria and gymnasium |
| Ortega ES | Replace HVAC system equipment at administration area, and install digital controls |
| Pecan Springs ES | Replace HVAC system equipment at administration area, and install digital controls |
| Pleasant Hill ES | Replace HVAC system equipment at kitchen |
| Read ES | Replace HVAC system equipment at selected classrooms, and replace one boiler |
| Reagan HS | Replace HVAC system equipment at gymnasium buildings |
| St. Elmo ES | Replace HVAC system equipment at cafeteria |
| Summitt ES | Replace HVAC system equipment at cafeteria, gymnasium and kitchen |
| Travis Heights ES | Replace HVAC system equipment at gymnasium |
| Travis Heights ES | Replace HVAC system equipment at cafeteria |
| Williams ES | Replace HVAC system equipment at kitchen |
| Williams ES | Replace one HVAC system chiller |
| Zilker ES | Replace HVAC system equipment at library |
TOTAL $20,391,325
ROOFING
| Austin HS | Repair/replace roofing at 200-classroom wing, gymnasium and weight room |
| Barton Hills ES | Repair/replace roofing over classroom areas |
| Blackshear ES | Construct canopy at southwest corner entry |
| Brown ES | Repair/replace roofing at 300-classroom wing, gymnasium and kitchen corridors and library |
| Burnet MS | Repair/replace roofing at 400-classroom wing, administration area and gymnasium dressing areas |
| Highland Pk. ES | Repair/replace roofing at 100 & 300-classroom wings, main corridor and administration area, kitchen, loading dock, and mechanical room |
| Johnston HS | Repair/replace roofing at classrooms 702-713, health services, print shop, culinary arts, and other selected areas |
| Reilly ES | Replace roofing and roof deck above kitchen and food preparation area |
| St. Elmo ES | Repair/replace roofing at 100 & 300-classroom wings and gymnasium |
TOTAL $4,458,073
BUILDING ENVELOPE
| Barton Hills ES | Replace deteriorated doors and frames at gymnasium |
| Brentwood ES | Replace windows at 300-classroom wing |
| Cunningham ES | Replace courtyard windows |
| Highland Pk. ES | Replace windows at administration area |
| McCallum HS | Replace courtyard windows at main corridor |
| Pearce MS | Repair/replace exterior wall cladding and weatherproofing flashing |
| Kealing MS | Construct direct exitway from science classrooms 109A & B |
| Reilly ES | Replace windows at cafeteria |
| Reilly ES | Replace windows at 400-classroom wing |
| Travis HS | Replace windows at 100 & 200-classroom wings, and reglaze windows at two-story 600-classroom wing |
TOTAL $2,910,189
SITE IMPROVEMENTS
| Allan ES | Replace sanitary sewer line at Annex |
| Anderson HS | Construct four additional tennis courts |
| Barton Hills ES | Improve site drainage at front of building and at portables |
| Casis ES | Improve site drainage at front courtyard and on south side of school |
| Fulmore MS | Replace sanitary sewer line at 500-classroom wing |
| Highland Pk. ES | Install security fencing between building wings |
| Joslin ES | Install security fencing between library and 100-classroom wing |
| Pearce MS | Improve roof downspout and site drainage |
| Reilly ES | Construct canopy for student pick-up |
| Reilly ES | Improve site drainage at front of school |
TOTAL $1,713,905
FUNCTIONAL INTERIOR IMPROVEMENTS
| Allan ES | Replace tile flooring at entry |
| Austin HS | Replace bleachers |
| Burnet MS | Replace bleachers |
| Davis ES | Replace moveable partition between cafeteria and gymnasium |
| Dobie MS | Replace bleachers |
| Doss ES | Install locking system for doors to classroom areas |
| Mathews ES | Construct built-in storage units for selected classrooms |
| McCallum HS | Replace deteriorated lockers along main corridor |
| McCallum HS | Replace bleachers |
| McCallum HS | Replace theater fly system at stage |
| Mendez MS | Replace bleachers |
| Mills ES | Renovate administration area for required visitor entry and replace entry canopy |
| Travis HS | Replace bleachers |
TOTAL $1,835,075
FIXED EQUIPMENT
| Crockett HS | Purchase automotive/collision equipment for Automotive Career Center |
TOTAL $318,500
GRAND TOTAL CRITICAL RENOVATIONS $37,213,068
|
|